What were you thinking? An exploration of human bias in subcontractor selection

December 04, 2018
By Rose Hall
P.E., CRIS, Head of Innovation, AXA XL
Subcontractor defaults on construction projects can be catastrophic, which makes selecting the right team of trade partners crucial. However, in a world where contractors make decisions both within the context of what they know about subcontractor candidates (hard data), and within the boundaries and limitations of their perceptions, world-view, and other biases, we see time and time again that despite any empirical evidence to the contrary, our decision-making processes are strongly influenced by the human factor. Psychologist Daniel Kahneman, noted for his groundbreaking work applying psychological insights to economic theory, says whatever else it produces, an organization is a factory that manufacturers judgements and decisions. He also says that one of the major biases in risky decision making is optimism. Therein lies the challenge in the chaotic and complex construction business, specifically, in the subcontractor selection process.
When contractors make “gut feel” decisions about subcontractor awards, they walk the proverbial tightrope of risk. It’s not that they don’t have guidelines to follow or best practices to lead the way. It’s simply that when it comes down to selecting who to work with, business is not actually about business; it’s about people. And people can and will be swayed from facts and data by their thoughts and feelings...their biases.
So how do we do it right? How do we use the industry best practices, and overcome the biases affecting our subcontractor selection process, while not completely abandoning the human element? Ultimately, how do we unbiasedly select the ideal trade partners that drive successful projects?
Build a strong case before applying the human element
Industry prequalification and subcontractor selection best practices exist to benefit and protect contractors. They help make the case for why a subcontractor should or shouldn’t be awarded a project in an organized, methodical manner and allow us to proactively address inherent risks. The first step in risk reduction is being mindful of deviations from what you know to be best practices, lest you begin down the alternate path down the rabbit hole of project risk. Let’s start by briefly outlining some industry best practices for subcontractor selection:
Financial Strength. Consider data points such as: Financial statements, with ratio calculations and year-over-year comparisons to reveal trends, credit and payment history. Are there any liens, past due accounts? What are their banking relationships like? Pull a D&B report, and look into their Surety Bonding. Do they have any legal issues to be concerned about?
Operational Strength. Consider both their depth and current capacity. Look at their organizational structure, corporate culture, insurance limits and coverage, risk management, years in business, subcontract modifications, supply chain, etc. Find out their historical annual, anticipated current year volume and projections for next year. What’s the largest project they’ve performed in recent years, their current WIP, pipeline, backlog, projects out-to-bid, and available man power? What’s their geographic strength, market segment, scope of work, level of complexity, skilled man power for definable features of work? Are there union/non-union and/or license requirements, etc.?
Safety Practices. Do they have a full time safety manager, appropriate support staff, a formalized safety program? Look up their OSHA 300 records, alcohol/drug testing, OSHA 30-hour trained personnel, safety goals, do they have 100% fall protection compliance. Does their safety culture align with yours?
Quality Practices. Do they have a corporate quality management program and a field quality management program in place? What are their pre-construction considerations? Will they engage in pre-installation meetings? Do they build functional mock-ups, perform third-party testing and design reviews? Do they request progress inspections, have punch list practices? Do they have commissioning, warranty management and water intrusion protocols?
Reputation and Track Record. Touchpoints such as post-bid/pre-award interviews are important to set up. Externally, running reference checks and listening to the rumor mill are essential for picking up anything you may have missed. Lastly, your most valuable internal resource is post-performance reviews from past projects with that subcontractor.
When subcontractor bias steers us wrong
Now that we have a framework for best practices, let’s walk through the project lifecycle from subcontractor selection, through failure to perform and remedy of default in an exploration of how our decision-making bias can affect project success.
PHASE 1: BID PHASE
Unrealistic Optimism + Denial of Risk – The bid is screaming low and you’re looking for a reason that despite the red flags in their prequalification package, this sub’s the right pick. You may be thinking: ‘I’ve never had a subcontractor default in the X years I’ve been building,’ or ‘They’ve been in business for 50 years! They’re solid.’, or ‘They’re too big to fail,’ or maybe even ‘we can control the risk!’. If your company experiences a subcontractor default only once per $100M of work, we as humans, have a tendency to have unrealistic optimism and round “rarely” to “never”. All of a sudden we’re in denial and making risky decisions due to unrealistic optimism.
PHASE 2: SUBCONTRACTOR SELECTION AND AWARD
Incentives, Goals and Authority – The bids are in, but none of bidders have all of the desired criteria. What do you sacrifice in order to make the job “go”? A good risk manager would pay attention to all the information. But in an imperfect world, what happens when there are tradeoffs between low price and safety, for example? We must examine our incentives and goals. How crucial is price (is the prime contract hard bid or negotiated)? How important is an EMR of 0.85 verses 0.70? Maybe the project is extremely complex and requires intricate quality control? Examining our incentives and goals, in conjunction with an authority matrix to ensure alignment will support solid decisions.
Anchoring + Satisficing - We generally assume the goal of decision makers is to choose among risky alternatives in order to achieve the ideal outcome. However, we see that optimization involves choosing an alternative that exceeds some criterion or target. While it’s true that we want to find the best combination prices and performance characteristics, there is the tendency to award (anchor with) the first subcontractor that provides a bid that meets: 1) Minimum performance standards; and/or 2) Matches budget/estimate in order to get on with the project (satisficing). When we are quick to make a decision, having anchored or satisficed, we settle for “good enough” and often miss out on the optimal outcome. This is the equivalent of someone saying, “Would you like a scoop of vanilla ice cream or…”, and before you hear the rest, you say, “Yes!” Since you like vanilla ice cream, this seems like a win. What you didn’t wait to hear was the rest of the question, “Would you like a scoop of vanilla ice cream…or three scoops of vanilla ice cream?” You have just satisficed yourself out of two extra scoops of your favorite ice cream.
PHASE 3: OEPRATIONS AND SUBCONTRACTOR PERFORMANCE
Belief in a Causal Basis of Events - Your project was going well, however now your subcontractor begins to display warning signs of distress. Never fear, you think. We will get them through! We will control their performance with a risk plan. Confidence is good, but here’s where you may overestimate your ability to control events. Ask yourself how much control do you really have over subcontractor performance? While some events may be manageable (e.g. loss of a key individual, cash flow issue, workflow issue, etc.), believing everything is manageable is likely an overestimation of your influence. A belief in causal basis of events lures us into a false sense of security by suggesting that if we caused the failure, surely we can cause the remedy! In subcontractor default we often see contractors attempt to manage or supplement a failing subcontractor for longer than is practical or profitable, rather than terminate them and onboard a new one. In this game, you have to know when to hold ‘em, know when to show ‘em, know when to walk away, and know when to hire someone else.
PHASE 4: SUBCONTRACTOR DEFAULT
Prospect Theory – As humans, our perception of a situation is directly affected by how it is presented to us. If I told you that you have a 20% chance of failure on a project, you are now thinking about failure itself, and 20% might seem risky. But if I said you have an 80% chance of success, well now you’re thinking about success and 80% looks rosy! Same odds, different presentation, different perception. So when we’re replacing that defaulted subcontractor, and all the replacement bids result in a savings, the decision-maker is likely to be risk averse. Since they narrowly escaped a catastrophic loss, and they stand to save money anyway, why take unnecessary risk? However, if the replacement bids all came in high and they are going to lose money anyway, decision-makers tend to become risk-seeking. Project teams will do anything to preserve budget and schedule, but they don’t always seem incentivized to take a chance on the upside. The same project manager that is unwilling to lose a guaranteed bonus for a shot at high rewards becomes risk-seeking when faced with decisions that guarantee losses. In the end, we dislike losing more than we like winning! This concept affects our decisions in an imbalanced manner.
PHASE 5: PROJECT CLOSE-OUT AND LOOKING TOWARD THE NEXT PROJECT
Success-Induced Bias - When we have a positive experience, we tend to give ourselves credit for executing our intentions; see history as a casual chain of events; or update our expectations for future performance and confidence. In fact, decision-makers are likely to be biased by recalling their own (recent) experiences in their memories. They attribute their successes to their abilities and their failures to their luck. Coming off of a successful construction project, we will remember our own contributions the best, and will give ourselves credit for executing our good intentions. Success makes us confident, which can cause us to underestimate risk and influence other (less successful) decision-makers. As a result, successful managers, who are by intention trying to be risk averse, could actually wind up being risk-seeking simply as a result of past successes, which in reality have no bearing on future outcomes.
Engineer a better approach to decision making under risk
How we can do a better job of choosing the right subcontractor for the job? But be sure to look at the whole picture, and that picture includes a balance of best practices and human decision-making. We must examine our entire process and most specifically how our biases influence that process, our view of the situation, which flavors our decisions, and determines the ultimate outcome.
To contact the author of this story, please complete the below form
More Articles
- By Industry
- By Region
Quick Links
Related Resources
- View All


Driving Program Business Success

Farm equipment losses can lead to financial disaster
Global Asset Protection Services, LLC, and its affiliates (鈥溕喽嗍悠礡isk Consulting鈥) provides risk assessment reports and other loss prevention services, as requested. In this respect, our property loss prevention publications, services, and surveys do not address life safety or third party liability issues. This document shall not be construed as indicating the existence or availability under any policy of coverage for any particular type of loss or damage. The provision of any service does not imply that every possible hazard has been identified at a facility or that no other hazards exist. 色多多视频Risk Consulting does not assume, and shall have no liability for the control, correction, continuation or modification of any existing conditions or operations. We specifically disclaim any warranty or representation that compliance with any advice or recommendation in any document or other communication will make a facility or operation safe or healthful, or put it in compliance with any standard, code, law, rule or regulation. Save where expressly agreed in writing, 色多多视频Risk Consulting and its related and affiliated companies disclaim all liability for loss or damage suffered by any party arising out of or in connection with our services, including indirect or consequential loss or damage, howsoever arising. Any party who chooses to rely in any way on the contents of this document does so at their own risk.
US- and Canada-Issued 色多多视频 Policies
In the US, the 色多多视频insurance companies are: Catlin 色多多视频 Company, Inc., Greenwich 色多多视频 Company, Indian Harbor 色多多视频 Company, XL 色多多视频 America, Inc., XL Specialty 色多多视频 Company and T.H.E. 色多多视频 Company. In Canada, coverages are underwritten by XL Specialty 色多多视频 Company - Canadian Branch and AXA 色多多视频 Company - Canadian branch. Coverages may also be underwritten by Lloyd’s Syndicate #2003. Coverages underwritten by Lloyd’s Syndicate #2003 are placed on behalf of the member of Syndicate #2003 by Catlin Canada Inc. Lloyd’s ratings are independent of AXA XL.
US domiciled insurance policies can be written by the following 色多多视频surplus lines insurers: XL Catlin 色多多视频 Company UK Limited, Syndicates managed by Catlin Underwriting Agencies Limited and Indian Harbor 色多多视频 Company. Enquires from US residents should be directed to a local insurance agent or broker permitted to write business in the relevant state.
色多多视频 as a controller, uses cookies to provide its services, improve user experience, measure audience engagement, and interact with users鈥 social network accounts among others. Some of these cookies are optional and we won't set optional cookies unless you enable them by clicking the "ACCEPT ALL" button. You can disable these cookies at any time via the "How to manage your cookie settings" section in our cookie policy.