Project Pursuits decisions affect subcontracting risks

July 29, 2019
By Cheri Hanes, CRIS, LEED AP,
Head of Innovation and Sustainability, North America Construction, AXA XL
As an industry, construction spends a tremendous amount of time and resources addressing the risks involved in subcontracting. The attitude is “We have a building to build, so we will make it work.” Our project teams are downright heroic in their willingness to do the daily work required to get a troubled subcontractor over the finish line, and most would say that’s just the job. To an extent, it is; subcontracting is inherently risky. BUT if we could proactively reduce that risk, how much more productive could our teams be?
Turns out, we have several tools for this, and I think one doesn’t get all the respect it deserves when it comes to protecting your subcontracting strategy: the project pursuit decision – also known as the Go / No Go process. Much of the risk of building - and especially subcontracting - is “baked in” at the very earliest stage of a project: the decision to pursue the work in the first place. The results of this decision-making process determine your subs’ potential for success or distress in dozens of ways.
Let’s take a look at some of the ways in which your Go/No Go can mitigate the risks of subcontracting or at least allow you to engage projects with your eyes wide open. What are the critical questions to ask?
Who are the players?
The parties involved in each project set the stage for a productive and collaborative workflow – or not. Who are the players and how do they influence sub risk?
The Owner or Developer – As soon as a potential project crosses your desk, you should start asking about your organization’s history with the owner. If they are new to you, find out what their reputation is amongst other Builders. What can you learn about their character and values? Will they be realistic and collaborative or idealistic and adversarial? Is their philosophy regarding project delivery aligned with your firm’s? A Win/Win attitude on the part of the owner empowers everyone to make intelligent decisions when issues arise. Your subs’ ability to get things done can be significantly impacted by an owners’ inability to compromise when constructability conflicts with a specific vision for a detail.
Understand if the owner has a history of success with the project type and geography. Buildings aren’t the same, and every variation carries its own specific risks. The risks of condos, for-rent, commercial, k-12, etc. are all distinct. Risks in South Carolina and South Dakota are very different. It matters if the owner is familiar with the differences and accommodating of the risk mitigation you are going to need - contractually and in the performance of the project - to protect your common interests. Do they have a defined risk strategy related to the project? If they do, does it align with your firm’s strategy? In the absence of history with the project type, are they at least able to articulate how they are intending to manage the project risks, and does their plan pass your “smell test”? If the owner is versed in the building practices for the type and geography, the likelihood of conflict over a sub’s work or schedule requirements goes down.
While you’re doing your diligence, take time to understand the owner’s reputation around payment. It can matter – quite a lot from a sub risk perspective – if they have a slow or contentious payment practice. “Pay when Paid” can seriously affect your subs’ ability to stay viable on your project, and a protracted dispute can spell disaster. Reasonableness has to be present in the process, and your detective work up front will provide many clues as to whether you can expect it.
Designer – Many of the same questions apply to designers. Have they delivered this type of project before? Do they have a reputation for delivering completely detailed documents and working through submittals and RFIs timely? Project-specific, vetted details prevent re-work. Keeping a clear and defined flow of work in front of your subs keeps them engaged on your project and working per the plan; waiting for an answer does not. Responsiveness matters if you don’t want your subs distracted and off track.
Your internal teams – Do you have the bench strength available for the project, with experience in the project type, size, geography, and market sector? Your project personnel are your primary assurance that the job will be done as intended. Subs can all perform their scope, their way, but if you want it done to your standards, you need people on site who know and can enforce them. New personnel, no matter their industry experience, simply don’t have the foundation of your practices to build on. Obviously, there will be times when a pivotal hire is made for a specific project, but a team with mostly new people or new people in leadership positions can lead to inconsistency, and result in challenges for your subs.
Sub Market – Understanding the strengths and weaknesses of the sub market in relation to your project puts you in an ideal situation for sound decision making. Considerations include:
- Labor – Sufficient workforce is maybe the hottest issue of our time. You must consider the size and schedule of your project against the available labor in the market. Important factors to consider include the presence of jumbo or high profile projects in the area likely to pull workforce and attention away from yours, or whether there is a project in the area known to be challenging from a sub perspective. It is also critical to understand whether you will be dealing with trades that broker work, and to consider if you are prepared to manage their production and quality if that is the case.
- Familiarity with Project Requirements – Are there scopes not typical to the area, for example, pre-cast in a place where it is not typical? This problem is most frequent when the designer is from a different region and is one of the reasons to understand the designer’s experience as described above. If this is the case, the subcontractors will likely be working in an unfamiliar medium, have logistical challenges, or travel from outside the region, and will therefore be hard to supplement or replace if they struggle to deliver their work.
- Special Project Requirements – Determine if the subs have experience delivering the required finish levels, insurance, safety practices, quality control, documentation and technological savvy required for the project. Consider whether it is likely that the subs in the area will be able to qualify for your subcontractor default insurance (SDI) program, or be able to provide payment and performance bonds if required. If your project has sustainability or other special requirements, you will also need to consider the subs’ experience with those particular standards.
- Minority or teaming requirements – If there are MWBE requirements or a goal on your project, it is important to understand the capacity of the qualified players in that space. It is a delicate balancing act between mentoring and/or helping a particular sub to grow, and encouraging them to “overeat”. When a sub fails spectacularly, it is more likely to be from taking on too much work too fast than not enough work. Do not award subs work that is not supported by their financials; it is necessary for them to stretch in order to progress, but calculations from your financial analysis can indicate whether what you are asking for will result in growth or failure.
Other factors in play
Contract and Bid type – Negotiated work puts your firm, and your subs, at an incredible advantage over hard-bid. It allows you and your subs to be involved early and influence constructability, empowers proactive teamwork, and lets you understand the subcontractors you are considering fully rather than being put in a quandary of whether to rely on an unknown sub’s number on bid day. If you take on a hard-bid project, do so in circumstances where you have excellent knowledge of the sub market, and a strategy to make quick, informed decisions around outliers. At a minimum, you need to be able to quickly understand their typical project size and reputation in the market.
The bottom line is that if your firm traditionally performs in one model, you may find the others to be challenging in unexpected ways, and that challenge may affect your subs as well.
Design Build and Integrated Project Design take the beneficial collaboration described above to another level, but there are considerations to be made around the additional liability you take on these models. The bottom line is that if your firm traditionally performs in one model, you may find the others to be challenging in unexpected ways, and that challenge may affect your subs as well. Consider carefully before switching spaces, no matter how tempting the project.
It is also important to consider whether the contract itself is generally fair. Does it allow for unforeseen conditions, force majeure events, or other project delays? Are there uncapped or excessive Liquidated and/or Consequential Damages? Are you held responsible for each milestone, or only the overall completion date? This may seem unrelated to your subs’ success on your project, but those provisions all flow down to them (right?) and defaults have resulted when that happens.
The reasonableness of the schedule also comes into play. In the ideal situation, the subs will have helped create the schedule, giving you reasonable certainty that they can meet the milestones. If that is not the case, ensure the schedule durations seem sufficient for the project type and size by asking them.
Geography – There are times when it makes sense to strategically enter a new market, but it is challenging. Where a project sits can be just as important as the project itself. Variations in codes, licensure, inspections, soils, typical scope inclusions/exclusions, and labor availability can all impact projects and merit careful consideration in your pursuit decisions. If the job calls for unusual materials, means, or methods required for the area, there is higher potential for subcontractor failure as they struggle to learn on the job.
It is also critical to account for the sub relationships you have in a new geographic market, and to your ability to analyze their capabilities against the demands of the job. In the absence of existing relationships, an effort to understand the sub market should involve not only getting to know the subs directly, but also conversations with local GCs, designers, industry groups, and suppliers to understand the subs better. This takes time and resources, and still does not fully eliminate the risks of doing business with subs unfamiliar to you. Consider the cost of this effort in your calculations.
Capacity is also a factor when moving into a new geographic market. The interplay between sub financial capacity and project size is challenging to assess in an unfamiliar market. One way to gauge this is to look at typical project sizes in the area. If your project is outsized for the area, take the closest possible look at the potential for splitting up sub packages by scopes or phases, and take that strategy into account in your pursuit decision.
Remote locations can also complicate things considerably. In a remote area, you may have only one option for a sub on one or more scopes; that is a recipe for pain, especially if combined with limited financial capacity. In the event of sub distress, you may have to nurse them along, manage their workforce, be their bank, or worse. If they fail anyway, bringing in a sub from outside the area will certainly come with a premium. As you make these considerations, pay special attention to critical path or specialized subs with the potential to be particularly disruptive to replace.
Climate/Seasonal Factors – Local weather conditions are risk factors too. In areas with extreme weather, seasonal access may come into play. Productivity factors, weather days, and sequencing certainly will, as may methods including temporary hoarding, heating or cooling for concrete, etc. Any of these challenges may cause a subcontractor to struggle to meet planned production.
In summary, taking these subcontractor related factors into consideration as part of your Go/No Go process can result in a greater likelihood of your projects coming in on time, on budget, and to the required standards with a minimum of stress. Include as many as possible when defining your Go / No Go practices, and really use them to make or break the business case for taking on the work. Chasing only the “right” work is best for everyone involved.
About the author: Cheri Hanes is a risk engineer with AXA XL’s North America Construction insurance business. She’s always open to talk more about CLT. Contact her at cheri.hanes@axaxl.com.
To contact the author of this story, please complete the below form
More Articles
- By Risk
- By Industry
- By Product
- By Region
Related Resources


Constructive Conversations: Taking tech to the jobsite

Subcontractor Operational Prequalification: Putting power in the process
Global Asset Protection Services, LLC, and its affiliates (鈥溕喽嗍悠礡isk Consulting鈥) provides risk assessment reports and other loss prevention services, as requested. In this respect, our property loss prevention publications, services, and surveys do not address life safety or third party liability issues. This document shall not be construed as indicating the existence or availability under any policy of coverage for any particular type of loss or damage. The provision of any service does not imply that every possible hazard has been identified at a facility or that no other hazards exist. 色多多视频Risk Consulting does not assume, and shall have no liability for the control, correction, continuation or modification of any existing conditions or operations. We specifically disclaim any warranty or representation that compliance with any advice or recommendation in any document or other communication will make a facility or operation safe or healthful, or put it in compliance with any standard, code, law, rule or regulation. Save where expressly agreed in writing, 色多多视频Risk Consulting and its related and affiliated companies disclaim all liability for loss or damage suffered by any party arising out of or in connection with our services, including indirect or consequential loss or damage, howsoever arising. Any party who chooses to rely in any way on the contents of this document does so at their own risk.
US- and Canada-Issued 色多多视频 Policies
In the US, the 色多多视频insurance companies are: Catlin 色多多视频 Company, Inc., Greenwich 色多多视频 Company, Indian Harbor 色多多视频 Company, XL 色多多视频 America, Inc., XL Specialty 色多多视频 Company and T.H.E. 色多多视频 Company. In Canada, coverages are underwritten by XL Specialty 色多多视频 Company - Canadian Branch and AXA 色多多视频 Company - Canadian branch. Coverages may also be underwritten by Lloyd’s Syndicate #2003. Coverages underwritten by Lloyd’s Syndicate #2003 are placed on behalf of the member of Syndicate #2003 by Catlin Canada Inc. Lloyd’s ratings are independent of AXA XL.
US domiciled insurance policies can be written by the following 色多多视频surplus lines insurers: XL Catlin 色多多视频 Company UK Limited, Syndicates managed by Catlin Underwriting Agencies Limited and Indian Harbor 色多多视频 Company. Enquires from US residents should be directed to a local insurance agent or broker permitted to write business in the relevant state.
色多多视频 as a controller, uses cookies to provide its services, improve user experience, measure audience engagement, and interact with users鈥 social network accounts among others. Some of these cookies are optional and we won't set optional cookies unless you enable them by clicking the "ACCEPT ALL" button. You can disable these cookies at any time via the "How to manage your cookie settings" section in our cookie policy.